After waiting a few days for the Driving Range Tee to dry off from the rain last Friday, work has begun on installing the irrigation. There are 18 sprinkler heads needed to irrigate the larger new tee, and all the pipe and heads were installed today. You will see in pictures below how it looks when they lay our the pipe and wire, as well as trenching the lines.
Tomorrow the irrigation crew will run the 6 inch main line that feeds the Tee area and both the putting and chipping greens. This should leave TDI the rest of the week to finish the tee box and move on to start shaping this body of the range! The dredgers have also eclipsed the 14,000 yards hauled mark and are nearing completion! We only have 4 more days to go in February so our goal of being finished March 1st might elude us. Never fear, as we should only be a week behind. Not too shabby figuring we were pushed back 2 weeks at the start because of permitting, and have weathered 2 snow storms along the way!