Sunday, June 29, 2014
Driving Range Divots
With the new Driving Range tee opening, please try and keep your divots close together in order for the grass to be as good as possible. Thank You!
Tuesday, June 24, 2014
Entire course is fertilized and ready to grow!
Yesterday we applied our annual fertilizer application to the golf course. This fertilizer was applied the using a large spreader truck. This truck is the most efficient way for us to apply granular fertilizer, as it can do all 27 hole in about 4 hours. This is incredibly fast compared to if our crew was to spread it in-house. By using the spreader truck, we can spread the fertilizer on a Monday and not disrupt golf at all. Any chance we can do maintenance practices without affecting play we try our best to do so. Take a look at the picture of the Spreader truck giving the entire driving range some fertilizer!
Saturday, June 21, 2014
#6 Master Plan Bunker Project
Over the last year, the grounds committee has been discussing how hole #6 could be improved. A short par 3, hole #6 was very straight with not a lot of difficulty. The decision was made to try and work with the master plan to improve this hole and make a more enjoyable golf experience. At the start of green-up this year we started mowing the fairway with a bend to the left. This is much like it was when the hole was originally designed and also brings the fairway bunkers into play a little bit more. The master plan for the golf course states that the design was to eliminate the bunker to the left of the green and build a "fore" bunker in the front middle of the green. A "fore" bunker is one that is far in front of the green, but deceptively looks like it is built into the front edge. This will hopefully intimidate a golfer who is trying to go for the green in two. As the hole plays now after the project, they farther left you follow the fairway up, the less trouble the green presents your 3rd shot. It took us 8 days total to do this transformation, and with the help of course architect Bob Cupp, we were able to make it fit in just as the master plan called for. Take a look a few pictures of how the process worked.......
Here they are elimintaing the old bunker and preparing to dig out the new front bunker......
Here they are elimintaing the old bunker and preparing to dig out the new front bunker......
Here is Bob Cupp helping us to get the final grade perfect. I can not Thank Bob enough for all his help over the last year with planning the project and every day knowledge of golf course construction. The man is truly an artist!
The finished product. Not bad for 8 days worth of work. I hope this little project helps to add some enjoyment to your next round of golf!
Tuesday, June 17, 2014
Creek Project a success
The reinforcing of #13 creek bank with boulders was a huge success. In order to address an issue of eroding creek banks, a decision was made to line the stream with boulders that would help to retain the dirt and support the banks. The new forebay is functioning very well, and will actually need cleaned out rather often as silt accumulates. Take a look at what the creek bank looked like before and after the boulders started to be installed...........
As you can see, the boulders make for a much cleaner look, and also stabilize the stream bank from further erosion. It is hard to remember how bad the old stream bank looked until seeing them side by side.
The finished product is quite the addition to hole #13. It creates a great view from the second shot, and also adds a little intimidation to warn the golfer that the water hazard is in play.
Sunday, June 8, 2014
Light at the end of the tunnel!
Greetings MCC Members,
It is
with great joy I can announce the final week of the Driving Range project is
upon us. Everything has finally worked
out in our favor, and the push is on to sod the remaining 6 acres of the
Driving Range. The last month of the
project has been a challenging one and I would like to share with you a few of
the things which have factored in to prolonging the Driving Range opening.
When
planning the Dredging and Driving Range project last summer, it was an optimistic
goal that all the work would be completed by May 1st. This date was chosen as a best case scenario,
but also to give us a goal in which to strive to achieve. Like most construction projects, we have
endured many challenges over the last 6 months.
Weather events, slow drying silt from the bottom of the pond, a shortage
of sod trucks, equipment failures and permitting have all played roles in
delaying the project. There is still a
half an acre area in the back corner of the range that has yet to dry out and solidify
completely. Two weeks ago a bulldozer
could not even navigate through this soft area without getting stuck. Weekly rains are also no help to this drying
process. It seems like every time we
have been blessed with a week of good weather to work the dirt, it rains just
in time to wet the soil and set us back a few days. At times the rains have even negated all the
progress made and forced us to spend valuable time re-doing things which were
already completed.
While
the silt removed from the lake took longer than expected to dry, it also
delayed the process of installing the irrigation and drainage in the
range. Once the drainage was finally
installed a few weeks ago we were able to withstand the rains much better and
not lose all the progress we made during dry days. Last Friday we finally completed the
irrigation system for the Driving Range and connected to the main line water
supply. A total of 85 irrigation heads were
installed and have the ability to water all the new sod that is being layed
this week. An industry wide shortage of
tractor trailer trucks used to haul sod has made it difficult for the sod farm
to deliver our grass in a timely manner, and also forced our project to come to
a standstill. One or two sod trucks do
not pose a problem in most cases, but when you need 30-35 trucks to deliver 6+
acres of grass in a week’s time, scheduling becomes an issue. Combine this large order of sod with a
shortage of available trucks, and it creates a very challenging, and no doubt
frustrating situation. When I was
informed a week ago that the sod farm had 35 trucks lined up for delivery over
the next 5 days I emphatically said “Bring it on”! The sod installation crews have been doing a
great job of laying 6 to 7 sod trucks a day, or the equivalent of an acre and a
half of surface area. After a week of sodding we are now about 90%
finished and await 3 more trucks Monday morning that will finish the job.
Once the
Driving Range is completely sodded, all the grass will need rolled, fertilized,
and some minor patch work in places that did not survive. This work will be done by our staff over the
next month to finish up the project, but will in no way prolong the opening of
the driving range. We will now focus all
of our efforts on hole 14 and restoring it back better than before. Sod has been ordered for the end of next week
and I feel that you will start to see progress every day. I apologize that restoring this hole has been
moved down the priority list as other problems and projects have arose.
All in
all I feel this was a very successful project, and that the club has improved
in many different areas because of it. Our
Driving Range is now one of the biggest and best in Georgia, the new wall on #3
adds beauty to the golf course, the fore bays on both ends of the lake #3/#13
are already doing a great job of retaining silt, and the lake itself looks as
good as ever now that it has been completely dredged. In
closing I would like to thank the membership of Marietta Country Club for your
patience, understanding and support through this long and tedious project. It has no doubt been an inconvenience at
times over the last 6 months, but the light is getting very bright at the end
of the tunnel. With just a few more days
of hard work ahead, everything will be back to normal and the new club
amenities can be enjoyed by all.
Thank you,
Mark Hayes
Grounds Superintendent
Thursday, May 15, 2014
Rock Wall on #3 is Finished!
The rock wall in front of #3 Green has been completed, which means all 27 holes are now open! The construction of the wall was a very long process through planning and permitting, but once the permits became official we wasted no time in finishing the project. The company we hired to build the wall did a great job, and reinforced the wall multiple ways to ensure long lasting strength. From start to finish it took exactly 3 weeks to build from the ground up, back fill and sod. Our staff was in charge of the finishing work of back filling the wall, installing drainage and sodding. This took us 4 days alone to finish the process, but the work turned out great. I would like to say THANK YOU to one of our members, Mr. John Davis. Mr. Davis was kind enough to help send a Semi-Truck to Alabama to pick up the Zoysia grass sod used to finish the area between #3 green and the wall. Due to a trucking shortage, without his help we could not have finished #3 or been able to play all 27 holes last weekend. Please tell Mr. Davis Thank You next time you see him for his generous act! Take a look at the pictures of the wall from start to finish.........
Thursday, May 1, 2014
May 1st!
Today is May 1st, and I am very sad to say that the project is not yet complete. This day has long been our goal to for opening 27 holes and the Driving Range, but many different factors have made our goal unobtainable. Recent weekly rains have slowed the drying process on the last 50% of the range, and even the Bulldozers doing the work continually get stuck while trying to finish up. Please know that we are still diligently working to put everything back together, and still hope to have all 27 holes open some time in the next week to 10 days. I do believe that everyone will start to see a lot more progress over the next 2 weeks. Saturday, we will start to sod the remaining damage from the haul road on #3, as well as finish #8 fairway. After this area is sodded, TDI will then start laying sod in front of the new range tee. The plan is to sod as much of the range as possible next week. We should have over half of the range complete by the end of next week, and the rest will be soon to follow. Once project we have been busy with is stabilizing the banks of the creek on #13 fairway. We have chosen to repair the stream bank with big boulders, weighing 2,000 to 3,000 pounds each. This should help to keep the bank from continually eroding over time, and also add a clean and aesthetically pleasing look to the stream. Take a look at the pictures below and see what you think. I plan on showing a complete chronological timeline of photos once the project is completed. We still have one more side to go!
Even though the project is a little behind schedule, we are still seeing improvements every day. We are all anxious for the project to be over and for the club to be running at its normal capacity once again! We are going to put our nose to the grindstone for the next few weeks and deliver the best product possible!