Sunday, September 6, 2015

Tennis Project Update

The Tennis project is still progressing nicely.  The drains have been installed between the courts, and we have poured a little less than half of the sidewalk which will run between the Clubhouse and the Tennis courts.  This weekend the crews are not taking off for Labor Day, instead they are laying the block walls for the raised seating area.  Once the walls are installed, we will have the roof company come in and set the posts for the roof structure.  Please take a look at the pictures to see the progress!