This picture was taken from between the tee box and green on hole #15. The yellow piece of equipment closest to the camera is the pump lowering the water level. We currently have the water 2.5 feet low, and it looks like this is all we will have to lower the pond to be able to complete the work. By keeping the water in the pond we can ensure the safety of the fish and wildlife. Notice on the left side of the picture is a large excavator used to dig a hole in the rough to the right of #14 green. This hole will be filled with the silt from the pond, and then covered back over and sodded. All of the dirt removed from the hole was transported along the cart path on #14 to help level out the abrupt drop off from cart path to playing surface. If you look on the right side of the picture you will see the large 60 foot reach machine we used to dig out lake #3. This machine is currently located in the cove between #14 green and #16 tee box. We have begun the project on this portion of the lake, and will finish it before moving to the other side of #14 green. This process should only take a few days, and we are hoping to be finished by the weekend and the predicted thunderstorms! With some favorable weather we should be able to complete the entire dredging of lake #15 in a few days!
Here are some closer up picture of the process we will use to dredge the smaller cove on lake #15. I will post pictures of the work in action to further illustrate the process in the days to come.
Here is John in the large excavator working dredging the left cove of #14 green. It is a tight fit for such a big machine, but they got about 30% of the material removed in just one day!
No comments:
Post a Comment